banner
The Project Climate Change Wind Farm Benefits How the scheme
has been improved
Wind farm myths How you
can help
Links Contact Us
spacer   spacer
  Welcome to the Lochluichart wind farm site  
  click to download  
     
 

Press statements

 
 

Latest press statement:
Community Benefits

Previous press statements:
Press release 20070501
Press release Community Council Ballot

 
 

Project information

 
 

Project developer

The project applicant is LZN Limited, a joint venture between the Lochluichart Estate and Infinergy Limited, the wind farm developer

 
   
 

The Site

The site is located on the higher land between Loch Glascarnoch and Loch Luichart approximately 18 km north-west of Dingwall, not far from the intersection between the A835(T) and the A832.  The land comprises mainly unenclosed grazed upland wet heath.

 
 

Grid Connection

The amended wind farm scheme would require a maximum power export of 66 MW. The existing 132 kV line between Mossford and Beauly carries the power from four existing hydro stations.

An independent review has been carried out and found that it would be feasible to upgrade the line. Local connection could then be made via an on-site substation and an underground line to the Mossford hydro power station west of Lochluichart.

A grid connection application has been made to National Grid with the intention of connecting into the existing Mossford to Beauly 132 kV line.

 
 

Ecology

Following consultation with relevant organisations, including Scottish Natural Heritage, the RSPB and Highland Council, ecological surveys have been commissioned and conducted on and around the site.

Bird surveys have covered seasonal visitors as well as those that nest locally including specific diver bird and grouse bird surveys.  In addition, specific surveys for water vole, otter, pine marten and badger have been carried out as well as a fisheries habitat survey.  Invertebrates, amphibians, reptiles and mammals have been observed and recorded.

The results of those surveys have enabled the design of the renewable energy park to be refined to avoid areas that may impact on any sensitive habitat for bird, animal and/or plant species.

Neither Scottish Natural Heritage or the RSPB have objected to the original application on ecology grounds.

 
  Other Environmental Issues

In addition to ecology, other important environmental studies have been conducted in consultation with all relevant organisations.
 
   
 

Construction

Construction of the renewable energy park would last between 14 to 19 months with activities largely restricted to the site itself. It is anticipated that the wind farm will have a 25-year life, with removal of the wind turbines and associated equipment when operations cease.

The access route for construction traffic starts at Cromarty Firth Port at Invergordon and includes the local access road to the A9(T) Tomich Junction, the A9(T) to Tore roundabout and the A832(T) to the proposed site access on the northern end of the site near the Loch Glascarnoch Dam. The delivery of larger components will be subject to a range of mitigation measures in order to minimise delays on local roads.

 
 

Economic benefits

The construction of the Lochluichart wind farm a represents a £53 million investment and creates a wide range of contract opportunities for local businesses. An independent economic assessment predicts that there is the potential for up to £29 million of this figure to be spent in the Highlands and Islands region. There would be ongoing contract opportunities on a smaller scale during the operational phase.

It is estimated that between 80 and 100 people would be directly employed during the 14 to19 month construction period.

 
 

Communities

Infinergy is proposing to establish a community fund equivalent to £2,000 per MW installed per year (approximately £132,000 per year or £3.3 million over the 25 year life of the wind farm).

The intention is that the fund will be independently managed by trustees drawn from the local community and allocated to a range of causes and initiatives

 
   
   
   
     
 

Further Information
Further information on the revised proposals for Lochluichart are given in the Environmental Statement Addendum. This document provides a description of the project and predicts the positive and negative environmental impacts that will arise, ranging from issues such as noise to visual impact. Copies of the Environmental Statement Addendum are available for public inspection at the Highland Council offices in Dingwall and Inverness, together with a number of local post offices. Copies can also be purchased by telephoning LZN on 01202 856800.

A Non-Technical Summary of the Environmental Statement Addendum is available for downloading below. This document provides a simple summary of the scheme in a non-technical language.

 
     
   
     
  < back to top  
footer